Lake St. Martin Emergency Flood Relief Channel Final Design & Construction Management - 2012

AECOM Canada Ltd.

Manitoba Infrastructure and Transportation assigned AECOM the tasks of detail and construction management of the Lake St. Martin Emergency Flood Relief Channel in mid- August 2011. Completion of the project by the November 1 deadline was essential as the construction site was located in a remote area only accessible by boat or helicopter. AECOM completed and modified the design of the outlet channel, provided construction management, monitored construction activities for environmental responsibility and impact and coordinated logistic support to the client and contractors. More than 100 pieces of equipment and 150 personnel excavated 1.4 million cubic meters of peat and till from the 6 km long channel in 60 days.